Auburn Mechanical Uses Innovative Techniques to Approach its Largest & Most Complex Project to Date

August 7, 2020

MCAA members are constantly innovating and trying new techniques on their projects. Auburn Mechanical is just one example. The MCA of Western Washington member has been building through the COVID-19 pandemic, using a lean approach and specialty systems to meet the Washington State Convention Center Addition Project’s sustainability goals.

Planning and constructing a massive civic project like Seattle’s Washington State Convention Center Addition (WSSC) is no small feat. After nearly 10 years of design and planning and 2 years of preconstruction, the $1.6 billion project is in the middle of construction. Once complete, the new convention center will include a 150,000-square-foot exhibit hall, 100,000-square-foot flex hall, meeting rooms, a ballroom, an outdoor terrace and three levels of garage parking.

The project, a joint venture between Clark Construction Group and Seattle-based contractor Lease Crutcher Lewis, is the largest project in Auburn Mechanical’s 42-year history. It is also one of the most complex.

A Lean Approach

When Auburn Mechanical was selected as the plumbing contractor for the 570,290-square-foot addition in 2016, team members immediately implemented lean principles, including co-locating with the engineering team to support design, constructability review, and to explore opportunities for pre-fabrication. Auburn Mechanical’s detailers contributed to building the project’s massive federated model, which was completely designed in Revit.

With a plumbing contract worth over $40 million, Auburn Mechanical’s team will have installed 36 miles of plumbing, including six miles of underground piping, on the eight-acre site by the time the project is complete.

Focus on Sustainability

The project, which focuses on sustainability and long-term functionality, involves several specialty systems, including a heat traced and insulated stainless-steel Blucher grease waste piping system. Two 24,000-pound grease interceptors were successfully flown, landed, and installed on site. Additionally, stormwater recycling and reclamation systems will be used for the restroom toilets, reducing water consumption.

A Somewhat Unique Methodology

The convention center is being erected using “billboard construction” methodologies, a technique that is somewhat unique to Seattle-area construction. This technique involves building vertical sections simultaneously instead of floor-by-floor and creates greater efficiencies on sites with limited laydown area.

For their part, Auburn Mechanical is executing layout for systems on the slab-on-metal decks with a fast two-day turnaround between each deck. For added efficiency, Auburn Mechanical’s pre-fabrication shop has built almost 500 toilet and urinal carrier banks and prefabbed additional components to support just-in-time deliveries to the congested site.

Essential Status Requires Exhaustive Safety Protocols

Deemed an essential project at the onset of the COVID-19 pandemic, construction never stopped as a result of Washington State’s Stay Home, Stay Healthy order. With over 2,000 construction workers on the project, exhaustive safety protocols were put in place, including custom portable handwash stations designed and fabricated by Auburn Mechanical.

Project Completion Schedule

Construction is scheduled to complete in early 2022, nearly doubling the capacity of the current convention center.

Related Articles
Steven G. Pettersen, Executive Vice President of the Minnesota Mechanical Contractors Association (MMCA), passed away on December 5, 2024. He will be sorely missed and fondly remembered by the entire MCAA family.…
The 2025 dues rates for construction and service hours will increase to $.10 per labor hour effective January 1, 2025. The minimum dues assessment is based upon 12,000 hours ($1,200) per branch office, and the maximum assessment is 300,000 hours ($30,000) per branch office. New dues reporting forms will be provided in advance of the January 1 date. Watch MCAA.org and the National Update for an announcement.…
MCAA’s Virtual Trade Show connects our contractor members with the members of MCAA’s Manufacturer/Supplier Council.…
Since adopting ServiceTrade, Hurst Mechanical experienced 25 percent growth in a single year, a testament to the efficiencies gained through the platform. In addition, using ServiceTrade to streamline preventive maintenance (PM) scheduling and management led the company to increase PM volume by 20 percent.…
Load More...